![]() ![]() You simply cannot use provisional sums in an unamended ECC contract. If items are included elsewhere in the BOQ and it is a remeasurable contract then should the quantity of these items be reduced? Alternatively should the quotation include all the aspects of the SSCC required to complete the provisional items of work? I think this is unreasonable and clearly the Contractor is trying to maximise profits. The Contractor has submitted a quotation which includes only minor costs for aspects such as PPE stating that the people, equipment and materials are included eleswhere in the BOQ. A typical example of one of the deleted items is to remove licensable forms of asbestos under controlled conditions and would require people, equipment and materials to complete. ![]() The original BOQ incorrectly included some provisional items (not described in the WI) that the PM deleted which triggered a CE under 60.6. I have a query on deleted BOQ Items on a live NEC3 ECC Option B.